Contract Planning Workbench [Drogemuller, CSIRO] 2002-056-C
Project participants and team members |
Robin Drogemuller | |
John Holland | Nick Windmeyer | |
Woods Bagot | Peter Hoskins | |
CSIRO | John Crawford, Robin Drogemuller- Project Leader, Cheryl McNamara, Gerardo Trinidad | |
University of Newcastle | Rod Gameson, Willy Sher, Peter Ward | |
RMIT | Guillermo Aranda-Mena | |
Central Node | Melissa James |
Project description |
This project will use the Industry Foundation Classes (IFCs) as the basis for developing a first draft construction schedule for buildings. It will also provide an interface to Common Point Project 4D to provide a 4D (3D + time) visual representation of the building process. Information about the elements in a building is available at the end of the detailed design process through the IFC data. The information about classes of building elements can be combined in order to plan activities. For example, there are 64 in-situ reinforced concrete columns on a floor in a building. Each of these columns contains reinforced concrete of a particular grade and reinforcing steel. The volume of concrete and amount of reinforcing steel can be calculated from the geometry of the building elements.
We know that the sequence of operations for concrete columns is:
1) place reinforcing bars
2) erect the formwork
3) prop the formwork
4) place the concrete
5) wait for the concrete to reach an appropriate strength and
6) strip the formwork.